International Meeting of Very Large Power Grid Operators
October 24-25, 2005, Beijing, China
Overview of Unified Power
System (UPS) of Russia
Key challenges
Mr. Alexander F. Bondarenko - Director on UES regimes control –
the General Dispatcher of System Operator
JSC В«SO-CDO UPSВ»
Russia
SO
Current synchronous area configuration
CDO
UPS
2
Kal
Li
La
North
West
Belarus
UCTE
Norw
Est
Middle
Volga
Center
Ukraine
Kaz
Turkey
Mon
Az
G
Arm
Siberia
Ural
North
Caucasus
Mol
Disconnected link
Finland
Iran
Turk
Uzb
Tadj
Kirg
East
SO
CDO
UPS
Overview
3
 1956 – formation of the EES USSR after interconnection of
the Center and Middle Volga Power Systems.
 1958-1978 – connection of PS of Urals (1958), PS of South
(now Ukraine, Moldova) (1962), PS of North-West (1966), PS
of North Caucasus (1969), PS of Kazakhstan and PS of
Siberia (1978).
 1979-1993 – Commissioning of 750 kV OHL: USSRHungary, USSR-Poland (1984), USSR- Romania (1986),
Bulgaria-Romania (1987).
 1993 – Formation of the intergovernmental Power Union of
the CIS and Baltic Countries
POWERFUL CROSS-BOARDER LINKS
 1962-1978 – 400 kV lines built, connection of Hungary,
GDR, Poland and Czechoslovakia PS, Romania (1963) and
Bulgaria PS (1965).
SO
CDO
UPS
UPS of Russia in General
4
 Russian Power Plants installed capacity – 207,7 GW
 In 2004 871,2 billion kWh -UPS of Russia power plants is made out total
Therm al - 64,8%
Nuclear - 16,6%
Hydro - 18,6%
 UPS of Russia annual maximum load fixed 2004/12/23, 18:00 was 134,7
GW with current frequency -50,02 Hz
Voltage level
 UPS of Russia power consumption in 2004
has made up total 865,7 billions kWh
 Whole spread of UPS of Russia bulk grid
of 110-1150 kV for 2005/01/01 is 419,3
thousand km
Length
1150 kW
817.0 km
750 kW
3 073.9 km
500 kW
35 712.1 km
330 kW
10 797.9 km
220 kW
88 389.9 km
110 kW
279 836.4 km
SO
CDO
UPS
Power Industry Restructuring
GENERATION
SALE
5
Market rules
Competitive
sectors
Pricing liberalization and
market participation
incentivising
DISPATCH CONTROL
NETWORKS
Trade system
administrator
Natural
monopolies
Trade Procedures
organization
Settlement of Accounts
organization
State regulatory role
reinforcement,
state property share
increase
Regulated
tariffs
В«SO-CDO UPSВ» JSC
Hierarchical Architecture
SO
CDO
UPS
6
Foundation of JSC «System Operator – Central Dispatch Office for
Unified Power SystemsВ» 2002 .
JSC «SO – CDO UPS» comprises :
• CDO UPS of Russia;
• IDO East, IDO Siberia, IDO Ural, IDO Middle Volga, IDO Centre,
IDO North Caucasus, IDO North-West
• 56 subsidiaries - Regional Dispatch Offices (RDO), separated
from regional vertically integrated energy companies
JSC «SO – CDO UPS» controls 4 RDO of independent energy
companies operation
CDO
IDO
4 IPS
IPS
IPS
RDO
7 IDРћ
IDO
RDO
RDO
RDO
56 RDO
System Operator fulfills dispatch control on the territory of more than 70 subjects of Russia
SO
CDO
UPS
System operator – in center of
competitive market infrastructure
SELLERS
Whole-sale
generating
companies
Regional
generating
companies
Electricity
System
Control
Grid companies
(federal & local)
Hydro
Nuclear
Independent
generators
Money
System
Conditions
System
Operator of UPS
TSA
Auction
results
Electricity
Money
Distributing
companies
Suppliers
BUYERS
Eligible customers
7
SO
CDO
UPS
JSCВ«SO-CDO UPSВ» Role at the Transitional
8
Period Market
From 01.11.2003 competitive market sector is launched in European
zone of UPS of Russia
From 01.05.2005 competitive market sector is launched in
Siberian zone
Maintenance of market subjects’ operation modes and fixing of
deviation initiatives
In the framework of
the wholesale market
competitive sector
functioning JSC
В«SO-CDO UPSВ» is
engaged with the
following tasks:
Design model synthesis and actualization
(nodal marginal price model)
Preliminary and calculated (final) dispatch schedules forming and
sending to subjects
Initial information collection for auction
Preparing of information on the power sold/supplied to wholesale
market
Besides actual balance management JSC В«SO-CDO UPSВ» maintains complete
technological support to the Russia UPS wholesale electricity market
SO
CDO
UPS
Key reliability challenges
9
System operator computational and analytical capabilities
increasing
Increasing of the power grid regimes controlling ability,
introduction of the frequency prime and secondary control
units
Influence on the grid improvement, power systems
and the grid development planning, and management
of the generating capacity technological reserve
creation
Active influence on the procedures of the
national standards reliability development
SO
CDO
UPS
Extension of the SO computational
and analytical capabilities
10
Introduction of the modern information systems
Introduction of the 8 information systems of the current power regimes
monitoring up to 2008 (SCADA/EMS) from the world leading vendors with
high practical experience
Introduction of the 56 information systems of the current power regimes
monitoring (SCADA/EMS) produced by the domestic vendor to the RDO
SO
CDO
UPS
Visibility power system increasing
11
Increasing of the quality and information transmitting on the current power
regimes parameters rate to the SO dispatching centers
within
the time-period from 2004 to 2008.
Development of the dispatchingtechnological network
Data transmission network development
Organization of the additional directions
of the dispatching-technological
communication
Increasing of the incoming tele-information data volume
Organization of the additional reserved
connection network
Increasing of the carrying capacity of the digital tracks
of the CDO-ODU
Organization of the additional access lines (“last miles”)
from the dispatching centers to communication
Setting of the additional directory numbers
operators
of the dispatching connection
Increasing of the general capacity of the
connection nodes
Introduction of the international protocols
of the IEC and ICCP information exchange
at the dispatching centers
Introduction of the new central acceptancetransmission stations of the tele-information with the
high speed of exchange
Setting of the supporting routers for the data
transmitting network
Creation of the Wide area measuring system – analogous to WAMS
Introduction of the new components, allowing to provide the dispatcher with
the operative information by introduction of the video projection dispatching
boards (BARCO)
SO
CDO
UPS
Dispatching center
of the North Caucasus IDO
12
SO
CDO
UPS
Wide Area Measuring System
13
Domestic name – Transients Monitoring System (TMS)
The goals of TMS development
The organization of IPS/UPS security monitoring system.
Monitoring of participation of control regions frequency power control and regulation
Verification of IPS/UPS power system digital model.
Monitoring of the dynamic features of the power system. Geographically
Capabilities distributed and synchronized by GPS systems high-frequency metering,
frequency, power flows and voltage angle registration and transmission to the
of the System
analytical centers.
Frequency metering precision – 0,001 Hz, power (P,Q) – 0,5%, angle - +- 10
Necessary
to do
Analogues
Set 38 registrators at the power units, distributed all over the territory of
Russia and CIS countries. Organize the communication channels. Create the
unified analytical center.
WAMS system has been known in the USA since 1980 and there are more
than 120 registrators at present. There are about 53 registrators in the WAMS
system at the UCTE power units.
SO
CDO
UPS
Location of the transients
Monitoring systems
14
SO
CDO
UPS
SO role at auxiliary services market and
in investments guarantee mechanism
Auxiliary
services
market
15
Frequency control
Voltage control
Power reserve ensuring
Guarantee mechanism for investments into generating capacities
for technological reserve improvement up to 2006
Determination of the power insufficient zones
Choice of options for power (electricity) shortage elimination
Preparation and carrying out of tenders for investor,
conclusion of agreement on provision of capacity technological reserve
Control over agreement execution and generating capacities technological
reserve provision
!
Realization of all these tasks is supposed
to be completely charged on SO
SO
16
CDO
UPS
Thank you for your attention!
System Operator
Central Dispatch Office for
Unified Power System of Russia
www. so-cdu.ru